KENDRIYA VIDYALAYA BHARATPUR Secondary Block Maintenance and Reparing work started in August 2021 by CPWD. We got handed over 22 Rooms and toilet sections (Around Half Building area Repairing and New Toilet Block Construction Work) in October 2024.
The remaining work is being completed and we expect to finish it in the middle of 2025.
One New Vocational Education Lab construction Work started In October 2024 and completed 50%
and expected to complete with in 1-2 Month and will be ready for next session 2025-26.